The Three Gorges Dam on the Yangtze River has been a dream for generations and will be one of the largest construction projects ever undertaken by mankind. This great dam, the largest of its kind in the world, will provide China with tremendous power generation and flood control services. It was in 1992 that the Chinese Government finally gave the go ahead for the scheme, some seventy years after Dr. Sun Yet-Sen, pioneer of the Chinese democratic revolution, first proposed the idea.
The dam site is 27 miles upstream from Yichang City proper, at Sandouping Town, 38km upstream from the Gezhouba Dam Lock, inside the third of the Three Gorges. It is planned to be by far the largest hydroelectric project in the world. The Project calls for the construction of a concrete dam, a hydroelectric power plant and a series of locks just below the scenic Three Gorges region. The project is designed to be built in three phases and is scheduled for completion in year 2009.
One of the largest construction projects ever undertaken in the world, the Three Gorges Project will forever change the face of the Yangtze River as we know it today. Possessing comprehensive utilization benefits mainly for flood control, power generation and navigation improvement. It will be a vital important and backbone project in harnessing and developing of the Yangtze River. Measures have been taken to preserve and move the historical and cultural relics found along its banks; however many scenic spots will be adversely affected. The most dramatic section of the river, what we refer to as "the heart of the Yangtze"-the area from the Three Gorges all the way upstream to Chongqing-will eventually be drowned by the completion of the Three Gorges Dam, an integral part of the Three Gorges Project.
Project Introduction The Three Gorges Dam will comprise three parts: the dam itself, the hydropower stations and the navigation facility.
Location: The chosen site is in Sandouping, northwest of Yichang city in Hubei Province and is located at the downstream entrance to Xiling Gorge, 40 kilometers upstream from Gezhouba Dam.
Project Schedule Expected to have a total duration of 17 years, the work has been divided into three stages.
5 years (1993 -- 1997) Preparation period and first stage construction. 6 years (1998 -- 2003) Second stage construction 7 years (2003 -- 2009) Third stage construction